Project Description

This project was for Matt McLane at Transwestern. Project scope entailed the repair and waterproofing of the concrete surface at the Canyon Center in Boulder. Total time until completion was 3 months. All work was performed per recommendations by Wiss, Janney, Elstner Associates. Repair cost: $106,000.

Location

Boulder, CO

Engineer

Transwestern

Services

repair and patch concrete, pressure wash, installation of high performance overlay, installation of urethane sealant